Senior housing project delayed

WINSTED — The Winchester Housing Authority (WHA) had hoped to begin construction of its newest proposed senior housing community this fall, but the timeline may have been delayed after the Planning & Zoning Commission tabled a vote to approve the project’s application at its meeting Monday.

Carriage Maker’s Place, a three-story building that would be built at the upper end of Gay Street, would offer a total of 32 apartments for area residents age 55 and older.

The complex, if approved, would be constructed in two phases: The first phase consists of 17 apartments and the second of the remaining 15.

In addition, parking would be provided on site for 26 cars, and a drop-off area in front of the building would also be constructed as part of the plan.

The new facility, if completed, will be the fourth senior housing complex operated by the authority in Winsted. The WHA also manages Greenwoods Gardens, Chestnut Grove and Laurel Commons.

Earlier this year the authority’s development corporation received a $200,000 loan from the state to fund the preliminary planning portion of the project, which allowed the group to hire an architect to finalize the required development plans.

The total cost of the project is estimated at $3.5 million.

Over the past several months, the authority’s development corporation has been working closely with the Winsted-based Northwest Community Bank to secure the funding necessary for the construction of Carriage Maker’s Place.

Winchester Housing Authority Executive Director Fred Newman told The Journal in January that 32 individuals had already requested that their name be entered onto the proposed facility’s official “interest list.�

Carriage Maker’s Place, however, is not the only project on the authority’s front burners. Its development corporation is also hoping to construct a new addition to one of its existing senior housing facilities, Chestnut Grove.

The complex, at 80 Chestnut St., currently has 80 apartments: 60 efficiency units and 20 one-bedroom apartments.

The proposed expansion seeks to add another 26 one-bedroom apartments.

Chestnut Grove’s current age restriction is 55, but the new addition would require that at least one household member be age 62 or older.

Also, following HUD guidelines, applicants would be required to meet gross income limits of $30,000 per year.

The Chestnut Grove apartment complex was built in 1971 with funding from the federal Department of Housing and Urban Development (HUD).

The authority has once again sought out HUD’s financial assistance for the expansion project, applying for a development grant through the federal department.

The authority is expected to find out from HUD sometime in April or May if the proposed addition has been approved.

Winsted’s Planning & Zoning Board unanimously voted to send a letter of positive recommendation to the Board of Selectmen regarding the expansion at its Feb. 22 meeting.

Latest News

Fallen tree downs power lines, blocks Route 112

Eversource crews work to repair damaged power lines after a tree fell near onto Route 112 just north of the Interlaken Inn on Monday, June 22.

Photo by Nathan Miller

LAKEVILLE — A tree fell on Route 112 Monday, June 22, downing power lines and blocking traffic north of Route 41 near the Hotchkiss Four Corners.

Eversource crews on scene at 4:45 p.m. said power lines were being repaired and utility service had been restored to customers in the area.

Keep ReadingShow less

Francis Lynehan

Francis Lynehan

DOVER PLAINS — Francis “Butch” Lynehan, 75, a twenty-year resident of Dover Plains, New York, formerly of Sharon, passed away unexpectedly on Thursday, May 7, 2026 at Vassar Bros. Medical Center in Poughkeepsie, New York.

Born Aug. 29, 1950, in Sharon, he was the son of the late William W. and Nellie (Kluun) Lynehan.

Keep ReadingShow less

Richard McGriff

Richard McGriff

TACONIC — Richard McGriff died unexpectedly on May 16, 2026. This is a collection of loving reminiscences.

With a smile like that and a laugh like that and a soul like that, how could you not love him? Macey Levin and Gloria Miller

Keep ReadingShow less
google preferred source

Want more of our stories on Google? Click here to make us a Preferred Source.

Juneteenth graduation celebrates Berkshire’s next generation of leaders

Cohort 2026 members Abigail Horace, Adam Liccardi, Adrian Lynch, Cameo Brown, Chauncey Dozier, Claudette Grant, Erline Saintilet, Harmony Edwards, Kamayue Gomes, Mackenzie Colvin, Otis West, Shadre Domingo, TJ West and Tyeesha Keele-Kedroe and Blackshires’ leadership team John Lewis, Patrick Danahey, Dubois Thomas and Julie Haagenson gather at the Blackshires City Hall Fishbowl alongside Mayor Peter Marchetti and city officials Michael Obasohan, Brandon Gill, Katherine VanBramer, Heather Brazeau, Justine Dodds and Jesse Tobin McCauley.

Provided

When designer Abigail Horace joined the Blackshires Leadership Accelerator, she was looking for support for her business, Casa Marcelo, which was founded in Salisbury in 2019. Through the Accelerator, she created the Black Berkshires Social Club, which creates culturally grounded social spaces for Black and BIPOC residents in the region. Throughout her experience, Horace found a community of peers invested in one another’s success.

“Finding Blackshires has been transformative,” Horace said. “Being a BIPOC founder in this region can feel isolating, and this community has changed that. They see my work, champion my business and have opened doors I couldn’t have opened alone.”

Keep ReadingShow less
Forged by curiosity: Art, craftsmanship and big fun with Izzy Fitch

Izzy Fitch at Battle Hill Forge in Wassaic.

Madi Long
I’m not really inventing anything new. I just tweak it a little bit.— Izzy Fitch

A steel praying mantis stands among garden accents at Battle Hill Forge in Wassaic, its folded forelegs ready for prayer and mischief in equal measure.

“She’s very nice,” said blacksmith, sculptor and Battle Hill Forge owner Izzy Fitch, patting the giant insect affectionately. Then he added, “Just don’t go out to dinner with her.”

Keep ReadingShow less
Unexpected subjects, familiar beauty in new Kent exhibits
Millerton-based artist Alexis England with her flamingo and mandrill portraits at Peggy Mercury in Kent.
D.H. Callahan

Kent Barns was alive with art on Saturday, June 13, as three new shows opened at Peggy Mercury and Kenise Barnes Fine Art, featuring a variety of fascinating paintings and drawings from four local artists.

Peggy Mercury, which in just two years has earned a reputation for curating remarkable collections of fine beauty products and accessories, continues to find exciting art to complement its offerings. The new show, “Portraits,” features four pairs of paintings by Millerton-based artist Alexis England. The “portraits” she paints, however, feature some pretty unexpected sitters.

Keep ReadingShow less
google preferred source

Want more of our stories on Google? Click here to make us a Preferred Source.

google preferred source

Want more of our stories on Google? Click here to make us a Preferred Source.