SHARON – In a newsletter to the community Aug. 6, First Selectmen Casey T. Flanagan addressed the termination of the Sharon Center School Solar Project. Green Bank ended the project, referencing unsuitable electrical infrastructure.
The electrical service to the school is rated for 1,200-amps. An increase to 1,600-amp service would be required to utilize the solar array. When Green Bank learned of the added expense, the project was canceled.
At this time there are no realistic alternatives to pursue.
The letter ended, “The Town will keep investigating opportunities to incorporate renewable energy technology at our facilities.”




Tiffany Lemelin, shelter manager, brushing Marsala upon arrival.Provided
Michael DeBarba, certified dog trainer working with Marsala.Jennifer Almquist
Marsala wins a heart.Jennifer Almquist

Sadie, center, a Carolina dog, plays with her friend Negra, a terrier mix. Bella Linda, the small poodle, has since been adopted.L. Tomaino
Wesley, a young, exuberant mix, is looking for an active home.L. Tomaino
Bonnie and Clyde, an affectionate terrier pair.L. Tomaino

Provided