LAKEVILLE — The public hearing for the redevelopment of Wake Robin Inn is over. Salisbury Planning and Zoning Commission now has two months to make a decision.
The hearing closed on Tuesday, Sept. 9, after its seventh session.
Michael Klemens, chair of P&Z, had warned at the opening of the proceedings that “this might be a long night” due to a last-minute influx of material from experts hired by Wells Hill Road residents William and Angela Cruger to oppose the project, but this turned out not to be the case.
These 11th hour submissions set a sour tone to the start of the meeting, with commissioner Robert Riva stating that it was “not very professional to pull this stunt on this Commission.” Riva said he had diligently reviewed the already substantial documentation provided by both the applicant and the opposing experts, and was surprised to find a “dump” of additional information submitted just hours before the meeting’s start time at 6 p.m.
Tensions were quickly eased, however, when William Cruger offered his concise summation of his platform’s opposition to the expansion, which is the second iteration of the project after an earlier version was withdrawn late last year.
“It’s important for you all to hear from me that there was never any disrespect intended to the Commission, the commissioners, and to the process,” Cruger said. He defended the last-minute submissions as an effort on the part of the experts to be thorough in their analysis: “Our intention… has been and remains to do our best to get whatever we think will be helpful in your deliberations into the record.”
The Crugers formally entered the hearing process as intervenors for the first application from Aradev LLC, the applicant, in the fall of 2024, meaning they and their hired consultants had full party status in the hearing proceedings. During this cycle, however, they chose not to petition for intervenor status, yet during this round of hearings their role has been similar. Klemens described them as having “almost intervenor status — not quite.”
William Cruger summarized the consultant’s findings for Aradev’s revised application, noting they found it to be “virtually identical in scale to the previous proposal.”
“Our position is that the proposed expansion would absolutely negatively impact the usefulness, enjoyment and value of the surrounding properties,” he said.
Aradev’s attorney Joshua Mackey countered by saying that the special permit conditions would elevate the currently non-conforming hotel in the zone, describing it as a “community asset that is improved, regulated, and safeguarded for generations to come.” He characterized Aradev as “the next steward of this storied property.”
After Mackey and Aradev co-founder Steven Cohen concluded their remarks, Klemens closed the hearing with no public comment, which he had stated would be the case at last week’s hearing session on Thursday, Sept. 4. Klemens said that P&Z will begin deliberating the proposal in early October after the commissioners have had the chance to review the information in the record.
A total of 45 letters, including the Crugers’ experts’ testimony, were submitted since the Sept. 4 meeting alone, alongside hundreds of pages of application materials and additional testimony.
As the Commission deliberates and reviews, all of this information is available for public viewing on the “Meeting Documents” subpage under P&Z’s section on the town website, www.salisburyct.us.
The Commission must issue a decision on the application by Nov. 13, the end of the statutorily defined deliberation window.







The plaque in memory of Susan Getzendanner is still on the lawn of the Academy Building, but the tree was destroyed in the July 4 storm.Patrick L. Sullivan