WEST CORNWALL — Crews will temporarily dewater a portion of Mill Brook to repair the rubble foundation walls of a house along Sharon Goshen Turnpike.
The Inland Wetlands & Watercourses Agency approved the application, submitted by Bruce Whiteford, at a regular meeting Tuesday, Feb. 3.
“There’s holes under the concrete wall and it’s scoured out, so that’s where they want to repair,” said Chairman Bill Hurlburt. Flowable concrete will be used in the compromised areas.
Water will continue to flow downstream around the sand-bagged work zone and equipment will be lowered in. The project is expected to take two weeks, weather permitting.
Crews were asked to notify Land Use Administrator Spencer Musselman before work begins.