WEST CORNWALL — The future site of the wastewater plant in West Cornwall was officially determined by the Board of Selectmen Tuesday, Feb. 17.
The site is located on Route 128 between the post office and the design studio. The town has long planned to use this grassy plot for the sewer facility, and a signed option to lease the land from property owner Eric Tietz made it official.
The land was assessed at $94,000, which will be paid to Tietz out of the Housing and Urban Development grant that is funding most of the wastewater project. Moving forward, the town will pay $800 per month for the life of the 50-year lease.
With the land secured, Cornwall can move forward with the permitting approval process, which could take more than a year. A firm is already under contract to build the facility once the permits are finalized.